Cleshar working around the clock at Wessex

2026-05-31

Cleshar working around the clock at Wessex

Cleshar working around the clock at Wessex

Our dedicated teams have been hard at work for Network Rail in Wessex.
During a 52-hour possession, we successfully completed 1.172 km of Category 02 rerailing.
In another 52-hour possession, our team delivered 1.71 km of Category 02 rerailing.
Across both sites, we ensured the full recovery of scrap rail, and installed new pads, nylons, and clips to maintain the highest standards.
Great work, team! Your dedication and expertise make all the difference